11 selected records: 9 campuses and 2 multi-site programs. This register is not a complete statewide census.

Source-qualified investment, power and stage. Scroll horizontally to inspect every field.
Project / programOperatorLocality labelScopeInvestment disclosurePower disclosureConfidence
AWS Virginia expansion programAnnounced programAmazon Web ServicesStatewideprogram$35B planned through 2040Not disclosed for this programAReviewed 2026-10-30
Google Virginia cloud and AI programAnnounced investment programGoogleStatewideprogram$9B announced through 2026Not disclosed for this programAReviewed 2026-10-30
Microsoft Boydton data centerOperating — operator confirmedMicrosoftMecklenburg CountycampusNot verified at campus levelNot disclosed in cited sourceAReviewed 2026-10-30
Google Loudoun County data centerOperating — operator confirmedGoogleLoudoun CountycampusNot separately disclosedNot disclosed in cited sourceAReviewed 2026-10-30
Google Prince William County data centerOperating — operator confirmedGooglePrince William CountycampusNot separately disclosedNot disclosed in cited sourceAReviewed 2026-10-30
Google Chesterfield County data centerAnnounced — current construction stage unverifiedGoogleChesterfield CountycampusPart of broader Virginia program; campus amount not disclosedNot disclosed in cited sourceBReviewed 2026-10-30
QTS Richmond 1Marketed campus — phased deliveryQTS Data CentersHenrico CountycampusNot disclosed in cited source238 MW critical campus capacity — operator specificationAReviewed 2026-10-30
QTS Ashburn 1Marketed campus — expansion stage needs confirmationQTS Data CentersLoudoun CountycampusNot disclosed in cited source55 MW+ DC1 specification; DC2 delivery not verifiedBReviewed 2026-10-30
QTS Manassas 1Marketed campus — master planQTS Data CentersManassas area — parcel jurisdictions require verificationcampusNot disclosed in cited source190 MW+ critical campus specification — planned buildoutBReviewed 2026-10-30
Vantage Ashburn III / VA3Marketed campus — full buildout not verifiedVantage Data CentersLoudoun CountycampusNot disclosed in cited source288 MW critical IT load — campus specificationBReviewed 2026-10-30
Vantage Fredericksburg / VA4Planned campus — operator targets first building in late 2027Vantage Data CentersFredericksburg area — parcel jurisdiction not verifiedcampusNot disclosed in cited source192 MW critical IT load — planned campus specificationBReviewed 2026-10-30

Program and campus figures may overlap; marketed capacity is not proof of energized utility service. Unknowns remain unknown.