QTS Ashburn 1

QTS markets a two-building, 28-acre Ashburn campus. Its page lists 55 MW-plus for DC1 and a separately described DC2 expansion.

Source review 2026-10-30Confidence BMarketed campus — expansion stage needs confirmation
Operator
QTS Data Centers
Record type
campus
Locality
Loudoun County
Region
northern-virginia
Investment disclosure
Not disclosed in cited source
Power disclosure
55 MW+ DC1 specification; DC2 delivery not verified
Jobs disclosure
Not disclosed in cited source
Status
Marketed campus — expansion stage needs confirmation

The source still labels DC2 under construction with a Q2 2026 target. Passing that target is not evidence of completion.

This record retains the source’s discrepancy rather than counting the expansion as delivered capacity.

Project status and disclosures are attributed to the cited source. Announced investment is not proof of expenditure, and utility capacity is not inferred from computing or building capacity.