Vantage Fredericksburg / VA4

Vantage describes its planned Fredericksburg VA4 campus at 225 Centreport Parkway as three facilities with 192 MW of critical IT load. This is a planned campus specification, not verified delivered utility capacity.

Source review 2026-10-30Confidence BPlanned campus — operator targets first building in late 2027
Operator
Vantage Data Centers
Record type
campus
Locality
Fredericksburg area — parcel jurisdiction not verified
Region
i95-corridor
Investment disclosure
Not disclosed in cited source
Power disclosure
192 MW critical IT load — planned campus specification
Jobs disclosure
Not disclosed in cited source
Status
Planned campus — operator targets first building in late 2027

The operator’s campus page describes an 82-acre site and a target for the first building to become operational in late 2027, with additional phases through 2028. These are operator delivery targets, not verified completion milestones.

The Fredericksburg postal label is not treated as proof that the campus is within the independent city’s boundaries.

Project status and disclosures are attributed to the cited source. Announced investment is not proof of expenditure, and utility capacity is not inferred from computing or building capacity.