QTS Manassas 1

QTS describes a 105-acre, planned six-building campus with 190 MW-plus of critical campus capacity in the Manassas area.

campusConfidence BDesk review 2026-10-30

Exact reviewed disclosures

Operator
QTS Data Centers
Locality label
Manassas area — parcel jurisdictions require verification
Source-attributed status
Marketed campus — master plan
Investment
Not disclosed in cited source
Power
190 MW+ critical campus specification — planned buildout
Employment
Not disclosed in cited source

The operator lists Godwin Drive addresses and future buildings. A postal address alone does not establish the legal jurisdiction of every parcel.

The full planned campus specification is not treated as currently operating capacity.

Questions the public record still needs to answer.

These are diligence prompts. General reference sources below are not verified project-specific approvals, utility agreements or incentive awards.

Land use and jurisdiction

Which parcel, legal jurisdiction and land-use approvals apply to QTS Manassas 1?

The reviewed locality label is “Manassas area — parcel jurisdictions require verification”. Confirm parcel jurisdiction independently. No locality-matched land-use reference is recorded in this packet; consult the actual governing jurisdiction.

Electric service

What site-specific utility service agreement, interconnection milestone and delivery date are documented?

Reviewed disclosure: 190 MW+ critical campus specification — planned buildout. A campus specification is not an energized utility commitment. The general utility and SCC references do not identify the serving utility, governing rate or service agreement for this particular site.

Reuse qualifications

  • This is a public research packet, not a legal, tax, engineering or investment opinion.
  • A source association is not proof of a final permit, utility commitment, incentive award or completed project.
  • Campus and multi-site program scopes are different. Do not sum overlapping program and campus investment or capacity figures.
  • Publication dates, desk review dates and project milestones have different meanings. An export is not a new source verification.
  • Unknown or undisclosed values remain unknown; locality markers are approximate and do not establish parcel jurisdiction.

Canonical record: https://virginiai.com/data-centers/qts-manassas-1