Vantage’s VA3 specification describes a 134-acre campus planned for seven data centers and 288 MW of critical IT load.

campusConfidence BDesk review 2026-10-30

Exact reviewed disclosures

Operator
Vantage Data Centers
Locality label
Loudoun County
Source-attributed status
Marketed campus — full buildout not verified
Investment
Not disclosed in cited source
Power
288 MW critical IT load — campus specification
Employment
Not disclosed in cited source

The owner’s campus page describes the planned scope. It is not proof that all seven buildings or the entire IT capacity are operating.

Capacity is retained as critical IT load and is not added to utility demand or backup generator ratings.

Questions the public record still needs to answer.

These are diligence prompts. General reference sources below are not verified project-specific approvals, utility agreements or incentive awards.

Land use and jurisdiction

Which parcel, legal jurisdiction and land-use approvals apply to Vantage Ashburn III / VA3?

The reviewed locality label is “Loudoun County”. Confirm parcel jurisdiction independently. County guidance is not a project-specific approval.

Electric service

What site-specific utility service agreement, interconnection milestone and delivery date are documented?

Reviewed disclosure: 288 MW critical IT load — campus specification. A campus specification is not an energized utility commitment. The general utility and SCC references do not identify the serving utility, governing rate or service agreement for this particular site.

Reuse qualifications

  • This is a public research packet, not a legal, tax, engineering or investment opinion.
  • A source association is not proof of a final permit, utility commitment, incentive award or completed project.
  • Campus and multi-site program scopes are different. Do not sum overlapping program and campus investment or capacity figures.
  • Publication dates, desk review dates and project milestones have different meanings. An export is not a new source verification.
  • Unknown or undisclosed values remain unknown; locality markers are approximate and do not establish parcel jurisdiction.