Skip to content
  • VIRGINIA AI, infrastructure & the local economy SOURCE-LINKED
  • TRACKER 11 source-backed records EVIDENCE FIRST
  • THE DESK Power · water · permits · workforce
VirginiAIResearch Desk
Virginia diligence packets →

QTS Richmond 1

QTS lists Richmond 1 as a 207-acre campus in Sandston with 238 MW of critical campus capacity. The specification is an operator campus figure, not a verified energized load.

campusConfidence ADesk review 2026-10-30

Exact reviewed disclosures

Operator
QTS Data Centers
Locality label
Henrico County
Source-attributed status
Marketed campus — phased delivery
Investment
Not disclosed in cited source
Power
238 MW critical campus capacity — operator specification
Employment
Not disclosed in cited source

The operator describes six facilities in the master plan and 2.3 million square feet of current space.

Building-level completion and delivered utility capacity are not established by the marketing specification.

Questions the public record still needs to answer.

These are diligence prompts. General reference sources below are not verified project-specific approvals, utility agreements or incentive awards.

Land use and jurisdiction

Which parcel, legal jurisdiction and land-use approvals apply to QTS Richmond 1?

The reviewed locality label is “Henrico County”. Confirm parcel jurisdiction independently. No locality-matched land-use reference is recorded in this packet; consult the actual governing jurisdiction.

Electric service

What site-specific utility service agreement, interconnection milestone and delivery date are documented?

Reviewed disclosure: 238 MW critical campus capacity — operator specification. A campus specification is not an energized utility commitment. The general utility and SCC references do not identify the serving utility, governing rate or service agreement for this particular site.

Reuse qualifications

  • This is a public research packet, not a legal, tax, engineering or investment opinion.
  • A source association is not proof of a final permit, utility commitment, incentive award or completed project.
  • Campus and multi-site program scopes are different. Do not sum overlapping program and campus investment or capacity figures.
  • Publication dates, desk review dates and project milestones have different meanings. An export is not a new source verification.
  • Unknown or undisclosed values remain unknown; locality markers are approximate and do not establish parcel jurisdiction.

Canonical record: https://virginiai.com/data-centers/qts-richmond-1